Swimming pool “Zhaiyk Samaly” Uralsk

DESCRIPTION

The construction of a swimming pool on a “full construction” in the north-eastern sector of Uralsk (between 4 th and 6 th district).

A two-storey building. There is a swimming pool, changing rooms, sauna, sanitary facilities, and attendants’ room on the ground floor. There are spectator stands, restaurants and administrative offices on the first floor.

Project parameters:

  • Building area – 2,348 sq.m.
  • Total area – 3,583 sq.m.
  • The number of tracks in the pool – 6
  • Track length – 25 m
  • The height of the tower diving – 3 m
  • Capacity of the stands – 296 seats

CHARACTERISTICS

  1. Location: Uralsk
  2. Project: new construction
  3. Client: Karachaganak Petroleum Operating B.V
  4. General Contractor: LLP “Bonita Engineering”
  5. Project implementation term: from June 2002 to September 2003